The results of the analysis successfully identified 60 risk events and 38 risk agents in the construction of utility piping and work civil PDAM Pam Jaya. 60 respondents involved in the study consisting of project managers, supervisors, and engineers on pipeline and civil works construction projects.
The first phase is the identification of risks and risk agents in the piping and civil works utility construction through the measurement of severity and occurrence levels to produce an aggregate risk priority (ARP), then conducts a risk mitigation analysis in the second phase. Research is conducted through two phases. The purpose of this research is to analyse risk management on piping and civil works utility construction using the house of risk model. The pipeline and Civil works construction project to meet the distribution of clean water needs in Jakarta through the Cooperation Agreement PDAM Pam Jaya and PT Pam Lyonnaise Jaya (Palyja) potentially generate various risks. Therefore, risk management is indispensable for the success of a construction project. Construction activities such as piping and civil works utilities always potentially pose a risk.